blue swirlEastern Busway





What's new

Staged busway gets green light

The Queensland Government has approved the Eastern Busway Concept Design and Impact Management Plan (CDIMP).

The Government has committed $465.8 million for the next section of the Eastern Busway. This funding is for property acquisition between Buranda and Cavendish Road, Coorparoo and construction of the 1.05km section between the South East Busway, Buranda and Main Avenue, Coorparoo.

Further stages of the Eastern Busway are ready for immediate delivery, should funding become available under the Commonwealth Government's Building Australia Fund.


Princess Alexandra Hospital to South East Busway

Construction of this 600 metre section began in July 2007 and is due for completion by late 2009.

View more information about the Princess Alexandra Hospital to South East Busway section, including traffic and construction updates.

South East Busway to Main Avenue

Queensland Transport has appointed Sinclair Knight Merz/Maunsell AECOM as the designer for this section.

The Government is now reviewing proposals from construction companies interested in joining Queensland Transport and SKM/Maunsell AECOM in an alliance to deliver this section.

Queensland Transport expects to have a constructor on board by Christmas, with construction on track to start in mid-2009 for completion by early 2012.

View more information about the South East Busway to Main Avenue section.


Project timeline

Project activitiesProject timing
identify Eastern Busway corridor late 2005 (completed)
consult on Terms of ReferenceNovember/December 2005 (completed)
consult on draft alignmentJune - July 2006 (completed)
consult on preferred alignment and draft Concept Design and Impact Management Plan (CDIMP)February - April 2007 (completed)
State Government approves CDIMPJune 2008 (completed)
construction of Princess Alexandra Hospital to South East Busway, Buranda sectionJuly 2007 - late 2009
construction of South East Busway, Buranda to Main Avenue sectionmid 2009 - early 2012
construction of further sectionsto be determined in future based on traffic levels and funding availability



Contact us

Phone
1800 550 277 (freecall)

Email
easternbusway@transport.qld.gov.au

Write to (no stamp required)
Eastern Busway Project Team
GPO Box 2439
Brisbane
Queensland 4000

Interpreter
13 14 50 (for people of non-English speaking backgrounds)

TTY
13 36 77 (quote 1800 550 277)

ad
Last updated 6 November 2008

Copyright | Disclaimer | Privacy | Other languages
© TransLink Transit Authority 2008